| CMDLN Timeline | ||
| September 29, 1987 | Karen Ahles submits Mid Minnesota Telecommunications Consortium Phase I request for proposal. Institutions involved are the technical colleges of Brainerd, Pine City, St.Cloud and Willmar. Donald Hamerlinck SCTC Director. | |
| November 15, 1987 | Funding is secured. Search for engineering consultant is initiated. | |
| December 1987 | Hire engineering counsultant. Research starts on classroom and transmission equipment. | |
| January-Feburary, 1988 | Prepare, submit and approve engineering design. Meeting begin with ECMECC, MSET, SCSU to explore programming options. Bob Hannu and Ed Lethert begin working on specs for classroom and transmission equipment for ITV classrooms. | |
| March-April, 1988 | Bidding process for the system is initiated. Select program to pilot. | |
| May, 1988 | Award bids and contract for system construction. Order equipment for classrooms and headend. Develop pilot program. | |
| June 27, 1988 | Karen Ahles submits Mid Minnesota Telecommunications Consortium Phase II request for proposal. | |
| June-August, 1988 | Construct system. | |
| July 30, 1988 | Secure funding. Present consultant retained to write specs on adding Alexandria, Anoka and increasing capacity to Pine City. | |
| August, 1988 | Hire Project Director. | |
| September, 1988 | Phase I System operational. Pilot programs begin. | |
| September, 1988 | Initiate bidding process for phase II. | |
| October, 1988 | Prepare orders for equipment. | |
| October-January, 1989 | Construct Phase II system componates. | |
| March, 1989 | Phase II system operational. | |
| Feburary 14, 1990 | Karen Ahles submits Mid Minnesota Telecommunications Consortium Phase III request for proposal. St.Paul will be added to the MidTec network. | |
| January, 1998 | Paperwork on the 'new' network starts. | |